Talbot Gateway - NEW NEW upate !!
It looks like work on the North Station extension will indeed resume
next April. Council documents have confirmed that Wilko's lease expires
then, so demolition will happen regardless of whether a new site for
them is ready (presumably they will move to a temporary location).
The full schedule looks like this:
April 2020: demolition and start of works.
March 2021: trams start run to a temporary terminus located where entrance to Wilko is now.
First quarter of 2022: trams start to run to the final terminus next to the new underpass.
Time to finally get this done so other projects are progressed in due course.
First quarter of 2022: trams start to run to the final terminus next to the new underpass.
Time to finally get this done so other projects are progressed in due course.